Family Islands Airports Renaissance Project Update

Family Islands Airports Renaissance Project Update

Bahamian Media News:

FAMILY ISLANDS (AIRPORTS) RENAISSANCE (AS OF MAY, 2026):

Since The Bahamas Government launched its aggressive Family Islands Renaissance Project, with 3 airports, the initiative has taken flight, now expanding to more than 19 aerodromes across the archipelago.

This represents the largest investment in Family Islands Airport Infrastructure ever made by any government in Bahamian history. THANKS TO OUR PROJECT PARTNERS!

THE RENAISSANCE has successfully touched TWENTY-ONE (21) ISLANDS, including: Abaco, Acklins, Andros, Bimini, Black Point, Cat Island, Crooked Island, Eleuthera, Exuma, Farmer’s Cay, Grand Bahama, Great Harbour Cay, Inagua, Long Island, Mayaguana, Moore’s Island, New Providence, Ragged Island, Rum Cay, San Salvador and Staniel Cay

COMPLETED PROJECTS:
RAGGED ISLAND – Duncan Town with a New Terminal – COMPLETED December 2021

GREAT HARBOUR CAY – Terminal and Airside COMPLETED December 2022

GRAND BAHAMA – Grand Bahama Domestic Terminal Renovation COMPLETED January 2023

NEW PROVIDENCE – New Providence, LPIA: Phase 1 Airside remediation – COMPLETED, March 2025

ABACO – Treasure Cay: Airside COMPLETED, December 2025

LONG ISLAND – Stellar Maris: Airside and terminal Improvements COMPLETED January 2026

MAYAGUANA

  • Mayaguana Airport Terminal: COMPLETED March, 2026

CAT ISLAND

  • Arthur’s Town: Airside remediation and new terminal, COMPLETED, April 2026

ACTIVE CONSTRUCTION PROJECTS:

BIMINI

  • South Bimini: Airside remediation and new terminal

CAT ISLAND

  • New Bight: Phase 1 Runway remediation completed, New Terminal and CFR Buildings

ELEUTHERA

  • Rock Sound: Airside remediation and new terminal
  • Governor’s Harbour: Terminal Renovation completed and Airside remediation
  • North Eleuthera: Terminal and associated airside works

EXUMA

  • Exuma International: Airside remediation and Terminal Construction
  • Black Point: Airside works and terminal
  • Staniel Cay: Airside works
    -Farmer’s Cay: New Terminal, Airside works

GRAND BAHAMA

  • Grand Bahama International, Freeport: Phase 1 comprehensive new U.S. and Domestic Terminal construction, runway remediation, flood mitigation

LONG ISLAND

  • Deadman’s Cay: Airside remediation and Terminal construction

CROOKED ISLAND

  • Colonel Hill: Airside works and new terminal

RUM CAY

  • Port Nelson: New Terminal

SAN SALVADOR

  • San Salvador International Airport: Terminal Renovations

IN THE PROJECT PIPELINE:

ABACO

  • Marsh Harbour: Terminal building Renovations, ATC tower and old terminal building demolition
  • Moore’s Island: Terminal works and Airside remediation
  • Treasure Cay: New Terminal
  • Sandy Point: Passenger Pavilion

ANDROS

  • Andros Town (Fresh Creek): Airside remediation and terminal construction targeted
  • San Andros: Finalization of plans for new Terminal Building and associated airside remediation

INAGUA

  • Matthew Town: New terminal

ACKLINS

  • Acklins Airport: Terminal upgrades

NEW PROVIDENCE
-LPIA expansion, hotel RFP

RUNWAY SOLAR LIGHTS INSTALLED AT:
Stella Maris, Mayaguana, Acklins, Crooked Island , Sandy Point, Moore’s Island, Treasure Cay, San Andros, Congo Town, Mangrove Cay, Fresh Creek, Great Harbour Cay, Black Point and Staniel Cay.

The post Family Islands Airports Renaissance Project Update appeared first on ZNS BAHAMAS.